Why China Built the Qinghai-Tibet Railway?
Political Significance
Located at the southwest border of China, India, Nepal, Bhutan and Pakistan, Tibet has the very important geographical position. It promoted the economic development of Nepal's northern mountainous areas, and helped Nepal to appear on the world political stage independently.
Economic Factors
As the limited industrial capacity of Tibet, the Tibetan economy highly depends on imports from mainland China provinces. It is an important issue to transfer goods in and out of the region.
Before the railway’s operation, the basic route was the Qinghai-Tibet Highway which was build in the 1950s and connects Tibet to the neighbouring Qinghai province. Each year, there are only less than a million tonnes of goods being transferred. After the new railway’s operation, it brought a significant reduction in transport costs increased goods’ movement. By 2010, about 2.1 million tonnes were carried by train. The operation of the Qinghai-Tibet Railway also has shortened the land transportation time of trade between major cities in mainland China and Nepal from 12 to 18 days to less than one week.
Social Implications
At the same time, the Qinghai-Tibet Railway strengthens ties of Tibet and other Chinese areas, promotes cultural exchanges between Tibetans and other ethnic groups, and enhances the need for national unity.
It is also expected to promote the development of Tibet tourism. Chinese state media ever reported that from January to July of 2007, Tibet had seen over 1.7 million arrivals - only slightly fewer than that of the whole 2005. In summer of 2018, the Qinghai-Tibet Railway has accepted 2.862 million passengers.
The History of the Qinghai-Tibet Railway
For centuries, Tibet was till cut off from the outside world by its remote location, extreme climate and geographic environment. The isolated region stopped all the explorers and travelers, until the operation of the Qinghai-Tibet Railway in 2006 when it connected Tibet to the rest of China.
1) In the 1950s, the CPC Central Committee decided to build the railway to Lhasa.
2) Since 1956, the first Survey and Design Institute of Ministry of Railways has carried out a comprehensive survey and design work for the over 2000km line from Lanzhou to Lhasa.
3)In 1984, the railway from Xining to Golmud was completed and opened to traffic.
4)In May 2002, the permafrost test on Qingzang Plateau was carried out.
5)In March 2003, the train track was laid through Kunlun mountain tunnel; in June, Tanggula Railway Station, the highest altitude in the world, was started to build; in August, the laying and erecting project of train track successfully passed through Hoh Xil depopulated zone.
6)In August 2005, the subgrade, tunnel, bridge and culvert works of the whole Qinghai-Tibet railway were basically completed; on August 24, the railway track was laid through Tanggula Mountain; on October 12, the track laying of the whole railway was completed.
7)On March 1, 2006, Qinghai-Tibet freight train started operation test; on May 1, Qingha-Tibet no passenger train started operation test; on July 1, the whole Qinghai-Tibet railway was put into trial operation.
A modern American train traveler Paul Theroux once wrote in his book "Riding the Red Rooster" that the Kunlun Range was "a guarantee that the railway will never get to Lhasa". But the assertion has been broken as a train coded "Qing 1" from Golmud to Lhasa runed through a 1,686-meter-long tunnel in Kunlun Mountain July 1, 2006.
The Future Connection of Qinghai-Tibet Railway to Nepal
In a meeting between Chinese and Nepalese officials on 25 April 2008, the Chinese delegation announced the intention to extend the Qinghai-Tibet railway to Zhangmu (Nepali: Khasa) , the China-Nepal border. Nepal had requested that the railway be extended to enable trade and tourism between both countries.
The Lhasa-Shigatse railway opened in August 2014. In June 2018, China and Nepal signed a series of agreements including the construction of Shigatse-Kathmandu railway during Nepali prime minister Oli's visit to China. Construction is expected to be completed by 2024.
Ask a question & Free Inquiry
-
12 Days Kailash Kathmandu Yatra
Tibet to Nepal Drive
from $1822 -
15 Days Kailash Mansarovar Yatra
Via Ngari Southern Route
from $1858
Ask a question & Free Inquiry